31.10.2023

This page contains samples of documents that are necessary when carrying out work at height. These are acts, orders, permits and work permits. PPR. Installation of technological pipelines piping technological equipment with painting and thermal insulation


PPR and technological maps for the installation of metal structures of buildings and structures are developed without fail during the construction, repair or reconstruction of buildings (warehouses, production bases, hangars, factory workshops, offices, gas stations, car dealerships, ...) and structures (tanks, overpasses, sports facilities, ...). Carrying out work in the absence of these documents is prohibited. This may entail a stop of work from the authorities of Rostekhnadzor, the Customer, if work is being carried out on its territory, or other interested parties. It is also important that such a violation is subject to fines and other administrative measures.

At the stage of organizational preparation for the construction project, the Contractor, under an agreement with a specialized organization or on its own, is obliged to develop and agree with the Customer a PPR, PPRk and technological maps for the installation of metal structures. All decisions provided for therein are binding.

We develop PPR, PPRk and technological maps for the installation of metal structures of any objects. We take into account all customer requirements and bring all approvals to completion. We eliminate the identified comments during the verification stages and add additional missing data free of charge within the framework of the signed contract. The price of preparation is determined based on the provided initial data.

Project for the installation of metal structures

When performing work on the installation of building frames, warehouses (beams, trusses, rafters, braces, columns, braces, ...), metal structures of tanks (bottom, racks, wall, roof, fences, stairs, stiffening rings ...) and trestles for pipes and cables (racks, connections, beams, stairs, supports and consoles of pipelines and cable lines, ...), etc. it is necessary to develop a work plan for the installation of metal structures.

The complete work permit, with reference to local conditions, distribution of installation work into stages and taking into account the work being carried out in parallel, is issued to the responsible contractor. In turn, he familiarizes all working personnel with it against signature.

Schemes for installation of metal structures consist of a plan of the building and structure, locations of installation equipment. The boundary of the dangerous zone of collapse from mounted structures is indicated on the construction plan in the form of a red line with flags. The PPR includes technological maps for individual methods of work performed.

Technological maps for the installation of metal structures

Technological maps for the installation of metal structures must include methods for performing work with fastening methods. In the case of fastening structural elements to bolted connections, the technical documentation indicates the sequence of stages for preparation and lifting to the installation site. The tension forces of the bolts are indicated if there are requirements for bolting with controlled tension or without it if there is none. When fastening to welded joints, it is additionally necessary to develop welding flow charts.

Installation of vertically standing elements before their final design fastening, the technological maps describe the method of temporarily fastening them with braces to existing structures. Thereby excluding their possible collapse of loose elements of buildings and structures. After final fastening, the metal structures are aligned and straightened. Maximum deviations are contained in the “Quality Control” section of each technological map.

The technical specification is not drawn up for the entire facility as a whole, but specifically for operations. For example: a technical map for the enlarged assembly of metal structures at the installation site, a technical map for the installation of beams and vertical braces by welding, a technical map for fastening horizontal braces with bolts with controlled tension. Fastening structures at height can be done both from lifts and from scaffolding and scaffolding. Technological maps are also being developed for these works.

PPRk for installation of metal structures

In addition to the project for carrying out work on the installation of metal structures, the development of PPRk is also being carried out. It involves the selection and placement of lifting mechanisms at the construction site. The selection of truck cranes for installation is carried out according to the load-height characteristics of the crane, the parameters of the object under construction and the weight of the elements being lifted.

The PPRk contains diagrams for slinging mounted elements, horizontal and vertical connections of cranes, safety requirements, diagrams of the location of slingers and the person in charge at the time of slinging, slinging and lifting, diagrams of the joint operation of the crane and lifts for people (if they are used at the site).

Size: 2.07 MBChapter: Date: 04/24/2017Downloads: 56

PROJECT OF WORK PRODUCTION

Installation of a free-standing anchor-corner support on the foundation for a 500 kV overhead line,

type U2 (rotation method)

You can download it in doc format

I General part

This work project (PPR) was carried out on the basis of order No. 1154 dated December 28, 2015 “On the assembly and installation of overhead line supports on the territory of the training ground of the personnel training center”

II Project composition

The PPR includes a technological map for the production of work using jib-type truck cranes, jib-type manipulator cranes, manipulator cranes and PS-1 hoists.

III Explanatory Note

In order to improve the qualifications of personnel in linear sections, gain practical experience in assembling and installing supports, increase readiness for performing ATS, as well as equipping a training ground, a Work Project for the installation of a metal free-standing anchor-corner support (type U-2) has been drawn up for further implementation of this project.

The weight of the anchor-corner support type U2 is 5.712 kg.

PPR includes the following stages of work:

Preparatory work. Preparation of the installation site (clearing snow);

Fastening the metal post of the anchor-corner support U2 to the foundation with mounting hinges;

Lifting and securing the support.

Completion of work.

No.

Sequence of operations

Job title

Group

according to EB

Qty,

people

Preparatory work. Preparing the installation site (clearing snow)

Assess the installation site where it is necessary to clear snow (relief, swampiness, soil condition, presence of uncleaned forest, large stones, fresh stumps).

At the installation site, determine the direction of the bulldozer's route moves.

Master

Electrician

Conduct targeted briefing to the brigade with registration in the work permit. The briefing must indicate safety measures during the work, the order of operations, the technology for performing the work, indicate the directions of the route moves of the bulldozer, and, upon completion of the work, indicate the parking place of the bulldozer. The brigade is allowed to work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Complete the work to prepare the installation site and place the bulldozer in its parking area. Clear the foundations of snow manually (with shovels).

Electrician -performer of the work (permitting);

Bulldozer driver- crew member

Complete the work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Fastening the metal rack of the anchor-corner support U2 to the foundation with mounting hinges

Check the compliance of the dimensions at the centers of the reinforced concrete footings (foundations) with the dimensions of the support, as well as the vertical marks of the foundations.

If deviations exceeding the established tolerances are detected, the support may be lifted only after the detected defects have been eliminated.

Inspect the structure of the support post being installed and make sure that there is no possibility of it falling. The presence of all bolted connections and structural elements of the support. Check tools, devices, protective equipment and materials.

Protect the danger zone with tape.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Conduct targeted briefing to the brigade with registration in the work permit. The briefing must indicate safety measures during work, the order of operations, technology for performing work, and the danger zone. The brigade is allowed to work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Brigade

Install the truck crane at the workplace in accordance with Appendix No. 1.

Truck crane operator- crew member

Master

(responsible

Install the hinges onto the support leg foundations (using wood blocks to align the hinge after installing the support) and onto the support shoes.

Truck crane operator- crew member

Sling the support post. Using a truck crane, bring the support stand and shoes to the foundations. Secure the support shoes to the hinges. At the place where the cable support is attached, install wooden spacers to prevent the support from touching the ground and to level the support horizontally.

Truck crane operator- crew member

Electrician (slinger) - team member

Attach two loop slings to the support post (at a distance of 17 m from the base of the support) and insert a Ø 23 mm mounting rope to the traction mechanism (in accordance with Appendix No. 2). Similarly, from the opposite side of the support, lead the cable to the brake mechanism.

Electrician - team member

Install a sling for lifting the support column with a release device, securing it to the crane hook. Place wooden pads under the sling (or inventory pads under the sling). (in accordance with Appendix No. 2).

Truck crane operator- crew member

Electrician (slinger)- crew member

Lifting and securing the support.

Arrange the vehicles in accordance with Appendix 1. Before starting to lift the support, remove uninvolved personnel from the danger zone (during the process of installing the stand, before moving the mechanisms, it is also necessary to remove uninvolved personnel from the danger zone).

Master -responsible work manager

(responsible for the safe performance of work using PS)

Bulldozer driver- team member;

The truck crane smoothly lifts the support. The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Raise the support post to a height of 200-300 mm.

Master -responsible work manager

Bulldozer driver- team member;

Truck crane operator- crew member

Check the serviceability of traction mechanisms, rigging devices, installation of braces, as well as the correctness and reliability of fastening of all rigging under load.

Master -responsible work manager

(responsible for the safe performance of work using PS)

The truck crane smoothly lifts the support. The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Raise the support post to an angle of 35-40 degrees from ground level. Remove the load from the truck crane and transfer it to the traction mechanism.

Master -responsible work manager(responsible for the safe performance of work using PS)

Bulldozer driver- team member;

Truck crane operator- crew member

Pull out the release device, releasing the hook of the truck crane. Move the truck crane to the transport position and remove it from the danger zone.

Truck crane operator- crew member

Electrician -performer of the work (permitting);

The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Install the support stand on the foundations.

Master -responsible work manager

Bulldozer driver- team member;

Install square washers on the rack shoes and screw nuts onto the anchor bolts. In this case, the nuts should not reach close to the surface of the rack shoes.

Electrician - team member

Use a traction machine to apply tension to the cable to slightly tilt the support post. Remove the hinges. Move the traction machine back smoothly to place the support stand on the foundations.

Master -responsible work manager

Bulldozer driver- team member;

Align the support post according to tolerances. If necessary, to level the support post, install shims between the fifth support and the foundation.

Master -responsible work manager

Electrician -performer of the work (permitting);

Tighten the nuts and locknuts of the anchor bolts. Weld the pads to the heel of the rack. Weld the washers of the anchor bolts on three sides.

Master -responsible work manager

Electrician - team member

Electric and gas welder- crew member

Completion of work.

The electrician climbs onto the support post with the endless rope block to the place where the rigging is attached, stands on the lanyard, securing the safety harness lines to the support structure, and secures the endless rope block to the support post.

Electrician -performer of the work (permitting);

Electrician - team member

Electricians on the ground should lift the installation tool along an endless rope in a cotton bag.

Electrician -performer of the work (permitting);

Electrician - team member

Electricians on the ground must hold the endless rope to prevent sudden lowering of the rigging. Lower the rigging and tools to the ground one by one.

Electrician -performer of the work (permitting);

Electrician - team member

The electrician, located on the support, lowers the endless rope block to the ground.

Electrician -performer of the work (permitting);

Electrician - team member

Remove the workplace, rigging, tools, equipment.

The whole brigade

Remove the team from the workplace

Electrician -performer of the work (permitting);

Complete the work.

Master -responsible work manager

Electrician -performer of the work (permitting);


PROJECT OF WORK PRODUCTION

INSTALLATION OF STEEL STRUCTURES USING THE QUICK-ERECTED TOWER CRANE LIEBHERR 26K.1

1. GENERAL PART

1. GENERAL PART

This work project was developed for the installation of metal structures using a quickly erected tower crane LIEBHERR 26K.1 at the site: "..." at the address: ...

According to SNiP 12-04-2002 "Labor safety in construction. Part 2. Construction production" paragraph 3.3, before the start of construction of the facility, the general contractor must carry out preparatory work on organizing the construction site necessary to ensure construction safety, including:

- clearing the territory;

- installation of construction site fencing;

- installation of a pedestrian protective gallery and walkway;

- installation of stands with fire-fighting equipment, information boards with entrances, entrances, locations of water sources, fire extinguishing equipment;

- laying temporary power supply and lighting networks;

- delivery and placement on the territory or outside of it of inventory sanitary, industrial and administrative buildings and structures;

- re-arrange communications (if necessary);

- cleaning the work site.

The completion of the preparatory work must be accepted according to the act on the implementation of occupational safety measures, drawn up in accordance with SNiP 12-03-2001 "Occupational safety in construction. Part 1. General requirements."

Basic standards and guidelines used during development:

- SP 48.13330.2011 "Construction organization" SNiP 01/12/2004;

- SNiP 12-03-2001 “Labor safety in construction”, part 1;

- SNiP 12-04-2002 “Labor safety in construction”, part 2;

- Methodological recommendations on the procedure for developing projects for carrying out work using lifting machines and technological maps for loading and unloading operations. RD 11-06-2007;

- PP-390 “Resolution of the Government of the Russian Federation on the fire safety regime”;

- SP 70.13330.2012 "Load-bearing and enclosing structures". Updated edition of SNiP 3.03.01-87;

- SP 126.13330.2012. "Geodetic work in construction. Updated edition of SNiP 3.01.03-84" ;

- SP 16.13330.2011 "Steel structures". Updated edition of SNiP II-23-81 *;

- PB 10-382-00* “Rules for the design and safe operation of load-lifting cranes”;
________________
* PB 10-382-00 do not apply. Federal norms and rules in the field of industrial safety “Safety rules for hazardous production facilities that use lifting structures” have been approved. - Database manufacturer's note.


- OST 36-28-78 "SSBT. Production processes. Rigging work. General safety requirements";

- OST 36-100.3.04-85 "SSBT. Installation of metal and prefabricated reinforced concrete structures. Safety requirements";

- GOST 24258-88 "Means of scaffolding. General technical conditions";

- GOST 12.1.004-91 "SSBT. Fire safety. General requirements";

- GOST R 12.4.026-2001* "SSBT. Signal colors, safety signs and signal markings";

- GOST 12.4.087-84 "SSBT. Construction. Construction helmets. Technical conditions";

- GOST 12.4.107-82* "Safety ropes. General technical requirements";
________________
* GOST 12.4.107-82 was canceled on the territory of the Russian Federation from 07/01/2013 with the introduction of GOST 12.4.107-2012. - Database manufacturer's note.


- GOST 25573-82 * "Cargo rope slings for construction. Technical conditions";

- GOST R 50849-96 "Construction safety belts. General technical conditions. Test methods."

Only trained and certified personnel are allowed to install structures. Installation teams must have appropriate qualifications.

A log of the assembly of installation connections must be kept at the construction site, indicating the names of the installers, the date of installation of the connections and installation methods.

2. TECHNOLOGY FOR CONSTRUCTION OF STRUCTURES

2.1 Previous work

By the time the construction of the metal frame of the showroom begins, the following work must be completed at the site:

- installation of bored piles;

- cutting out trenches for grillages;

- arrangement of grillages;

- backfilling;

- construction of an inspection hole.

All work must be performed in accordance with the working design and documented in the Acts.

2.2 Preparatory work

Before starting work on the installation of metal structures, you should:

- clean the grillages from dirt, sediment and concrete deposits;

- incoming quality control of metal structures entering installation;

- use a pencil or marker to mark the marks of the installation, longitudinal axes on the side faces of the structures.

2.3 Installation work

Installation of structures should be carried out using grips in accordance with sheets of graphic part 2-5. It is preferable to install elements “from wheels”. If necessary, use an area in the northern part of the construction site for storing elements (see Stroygenplan).

As the columns and half-timbers are installed, sections of load-bearing reinforced concrete walls (elevator unit) should be erected.

Before installing the load-bearing beams of the coating at elevation. +6,800 (top of the column, bottom of the beam) within grips 1 and 2, it is necessary to mount the beams of the mezzanine floor at elevation. +3.585 (top of the beam) and erect a section of monolithic flooring.

2.3.1 General sequence of work on installing a metal frame:

1. At the storage site, prepare columns, beams and connections for installation.

2. Install the columns in the design position. Install each column in the following technological sequence:

- Perform slinging of the column.

- Raise the column above ground level by 300 mm, make sure that the slings are securely fastened.

- Turn the column by lifting it while simultaneously turning the boom (or changing the reach) to the stop so that the vertical position of the crane's cargo ropes is maintained.

- Use a LIEBHERR 26K.1 crane (can be replaced with one of similar characteristics) to move the column to the installation site. The column should be delivered to the installation site at a height above 2300 mm away from obstacles encountered along the way.

- When installing a column on a foundation, clean the threads of the anchor bolts from rust and concrete residues with steel brushes, run them with a drill with the appropriate diameter and thread pitch, and check for axial marks.

- Install the column on temporary mounting pads, ensure temporary fastening and alignment of the column on the anchor bolts with paired nuts that fix the position of the base plate.

- Carry out design fastening of the column to the foundation. If necessary, brace the column in two mutually perpendicular directions using struts.

- After installation, unstrap the columns.

3. Install the beams in the design position. Install each beam in the following technological sequence:

- Installers should install a scaffold at the location where the beam is to be installed.

- Sling the beam.

- Use a LIEBHERR 26K.1 crane (can be replaced with one of similar characteristics) to move the beam to the installation site. Bring the beam to the installation site at a height of 500 mm from any obstacles encountered along the way.

- The installer should approach the place where the beam is connected to the column from the scaffold and perform their design fastening. Upon completion of work on securing the beam, the slinger unfastens the elements.

4. Mount the connections in the designed position. Install each connection in the following technological sequence:

- Installers should install a scaffold at the communication installation site.

- Perform slinging connection.

- Use the LIEBHERR 26K.1 crane (can be replaced with one of similar characteristics) to connect the connection to the installation site. The connection should be delivered to the installation site at a height above 500 mm away from obstacles encountered along the way.

- The installer from the scaffolding should approach the place where the connection is connected to the beam and column and carry out their design fastening. Upon completion of work on securing the beam, the slinger unfastens the elements.

5. Mount the purlins in the designed position in the following technological sequence:

- Installers should lay temporary flooring from boards 40 mm thick (in two mutually perpendicular layers) along the load-bearing beams.

- Perform slinging of the purlin.

- Using a Liebherr 26 K.1 crane (can be replaced with one of similar characteristics), move the run to the installation site at a height above 500 mm from obstacles encountered along the way.

- The installer should approach the place where the purlin is attached to the beams from the scaffold and carry out the design fastening. Upon completion of work on securing the girder, the slinger unslings the elements.

6. Carry out a visual inspection and draw up a report on the work performed.

Loads must be slinged in accordance with slinging diagrams. For work, slings should be used that correspond to the weight and nature of the load being lifted, taking into account the number of branches and the angle of their inclination; the slings should be selected so that the angle between their branches does not exceed 90°.

Loads must not be moved while there are people underneath them. The slinger can be near the load while it is being lifted or lowered if the load is at a height of no more than 1000 mm from the platform level.

2.3.2 Crane operation

The work is carried out using a quickly erected tower crane LIEBHERR 26K.1 (can be replaced with a similar one in terms of characteristics).

Preparation of the workplace

Before starting work with a crane, you must complete:

- install stands with sling diagrams and a table of load weights in the crane operating area and at the storage area;

- install safety signs, sign No. 3 along the boundary of the dangerous zone, sign No. 2 along the line limiting the crane service area.

Crane operation when installing columns:

The crane operates with a hook lift height limit of 11.05 m, with a maximum reach of 24 m and a danger zone of 8.3 m when installing elements, as well as with a reach of 23 m and a danger zone of 1.7 m during operations at the storage site and when unloading from motor transport.

Crane operation when installing beams and ties:

The crane operates with a hook height limit of 11.4 m, with a maximum reach of 24 m and a danger zone of 3.6 m, as well as with a reach of 23 m and a danger zone of 1.6 m during operations at the storage site and when unloading from vehicles.

Crane operation when installing purlins:

The crane operates with a hook height limit of 9.2 m, with a maximum reach of 24 m and a danger zone of 3.5 m, as well as with a reach of 23 m and a danger zone of 1.3 m during operations at the storage site and when unloading from vehicles.

During unloading and installation, loads should be moved parallel to the boundary of the danger zone and prevented from accidentally turning around using flexible guy ropes. The lifting height of the hook should be limited to 6.0 m.

Prohibit the presence of people and the storage of cargo in the danger zone. Measures for the safe operation of cranes should be issued as a supplement to production and job descriptions for personnel operating load-lifting cranes and engineering and technical workers.

Close access to the work area for unauthorized persons not directly related to the work, for which purpose, before starting the crane operation, place a signal fence along the border of the dangerous zone.

Loading and unloading operations

General requirements

At the construction site, reinforcement and formwork elements are unloaded with simultaneous placement on the storage and edging site, individually or in stacks. Dragging loads is prohibited. When storing formwork elements in stacks, lay them in rows in a horizontal position no higher than four rows in height. Spacers with a width of at least 5 cm are laid between horizontal rows.

Before starting work:

- appoint the required number of slingers and signalmen;

PROJECT OF WORK PRODUCTION

PROJECT OF WORK FOR INSTALLATION OF TECHNOLOGICAL PIPELINES FOR LINKING TECHNOLOGICAL EQUIPMENT WITH PAINTING AND THERMAL INSULATION DEVICE KUPNK. Title 205

PROJECT OF WORK PRODUCTION
FOR INSTALLATION OF TECHNOLOGICAL PIPELINES LINKING TECHNOLOGICAL EQUIPMENT WITH PAINTING AND THERMAL INSULATION DEVICE KUPNK. Title 205

1 GENERAL DATA

A work project is an organizational and technical document for production purposes, which regulates the rules for conducting construction work and the deadline for their execution, the procedure for engineering equipment and arrangement of the construction site, and labor protection and safety measures. The work project determines the technological discipline at the construction site, the quality, timing and safety of the work.

This work project was developed for the installation of process pipelines piping process equipment with painting and thermal insulation.

The project was developed based on the following sets of drawings:

- 5747203-(367-2/08)-3022-205-TI;

- 5747203-(367-2/08)-3022-205-TI.VIT;

- 5747203-(367-2/08)-3022-205-TI.THM.

The work process is regulated by the following regulatory and guidance documents:

1. SNiP 12-01-2004 "Organization of construction";

2. SNiP 3.01.03-84* “Geodetic work in construction”;
________________
* SNiP 3.01.03-84 are not valid. In exchange, SP 126.13330.2012 applies

3. SNiP 3.02.01-87* "Earth structures, foundations and foundations";
________________
* SNiP 3.02.01-87 are not valid. Instead, SP 45.13330.2012 "Earth structures, foundations and foundations. Updated edition of SNiP 3.02.01-87" was put into effect. - Database manufacturer's note.


4. SNiP 3.03.01-87 "Load-bearing and enclosing structures";

5. SNiP 3.04.03-85 “Protection of building structures and structures from corrosion”;

6. SNiP 3.01.04-87 "Acceptance into operation of completed construction facilities. Basic provisions";

7. SNiP 12-03-2001 “Labor safety in construction” part 1;

8. SNiP 12-04-2002 “Labor safety in construction” part 2;

9. SP 12-135-2003 "Labor safety in construction. Industry standard instructions on labor protection";

10. PPB-01-03* "Fire Safety Rules in the Russian Federation", Ministry of Emergency Situations;
________________
* PPB-01-03 don't work. Instead, the Fire Regulations in the Russian Federation apply. - Database manufacturer's note.

11. GOST 23407-78 "Inventory fencing for construction sites and construction sites";

12. GOST 21779-82 "System for ensuring the accuracy of geometric parameters in construction. Technological tolerances";

13. GOST 7566-94 "Metal products. Acceptance, marking, packaging, transportation and storage";

14. GOST 24846-81 "Methods for measuring deformations of the foundations of buildings and structures";

15. GOST 2246-70 "Steel welding wire. Technical conditions";

16. GOST 23279-85 "Welded reinforcement mesh for reinforced concrete structures and products. General technical conditions";

17. GOST 5781-82* "Hot-rolled steel for reinforcement of reinforced concrete structures. Technical conditions";
________________
* GOST 23279-85 was canceled in the Russian Federation from 07/01/2013 with the introduction of GOST 23279-2012


18. GOST 5264-80 "Manual arc welding. Welded joints. Basic types, structural elements and dimensions";

19. GOST 9467-75 "Coated metal electrodes for manual arc welding of structural and heat-resistant steels. Types";

20. GOST R 52085-2003 “Formwork”;

21. GOST 21.101-97 "Basic requirements for design and working documentation";

22. GOST 24297-87* "Incoming product inspection";
________________
* GOST 24297-87 was canceled in the Russian Federation from 01/01/2014 with the introduction of GOST 24297-2013. - Database manufacturer's note.


23. GOST 28013-98 * "Construction mortars. General technical conditions";

24. GOST 7948-80 "Steel plumb lines for construction. Technical conditions";

25. GOST 9416-83 "Construction levels. Technical conditions";

26. GOST 7502-98 * "Metal tape measures. Technical conditions";

27. GOST 427-75 * "Metal rulers. Technical conditions";

28. GOST 12.3.002-75 "System of occupational safety standards. Production processes. General safety requirements" ;

29. GOST 12.1.004-85* "System of occupational safety standards. Fire safety. General requirements";
________________
* GOST 12.1.004-85 is not valid. Instead, GOST 12.1.004-91 applies. - Database manufacturer's note.


30. POT RM-007-98* “Inter-industry rules for labor protection during loading and unloading operations and placement of cargo”;
________________
* POT RM-007-98 are not valid. Instead, by order of the Ministry of Labor of Russia dated September 17, 2014 N 642n, the Rules for labor protection during loading and unloading operations and placement of cargo were approved. - Database manufacturer's note.

31. RD 10-40-93 "Standard instructions for engineering and technical workers to supervise the safe operation of lifting mechanisms."

The work project contains:

General provisions, list of equipment and personnel;

- technological map for installation of column block piping;

- technological map for painting the lining of the column block;

Technological map for insulating the piping of a block of columns;

- safety instructions.

Water supply is from the existing water supply.

Electricity supply for the construction period is provided from a distribution cabinet at the construction site, which is powered from the existing power line.

To ensure fire safety during construction, use an existing fire hydrant.

The work project provides for the use of modern means of mechanization of construction processes, compliance with labor protection and safe work requirements, and implementation of environmental protection measures. All workers involved in construction must be trained and have qualification certificates and must be provided with safety helmets and safety vests.

2 ORGANIZATION OF WORK

2.1 Preparatory period

Before starting work at the construction site, the following activities must be completed:

- The work manager, together with the Customer, must issue an approval certificate for construction and installation works on the territory of the existing enterprise, in accordance with clause 4.6 of SNiP 12-03-2001 “Labor safety in construction. Part 1. General requirements in the form of Appendix B;

- appoint by order persons (from among the engineers) certified in the field of industrial safety and having a certificate corresponding to qualifications, responsible for labor protection, quality and proper performance of construction and installation work, fire safety, responsible for the good condition and safe operation of gas and hydraulic machinery and equipment, etc. .d.;

- develop measures for the safe conduct of construction, installation, commissioning and other types of work at the facilities of launch complexes in the conditions of existing production in the form of Appendix No. 6 of instruction No. P2-01 SP-218 I-001;

- issue a permit for construction and installation work in places where hazardous or harmful factors are present, in accordance with clause 4.11 of SNiP 12-03-2001 “Occupational Safety in Construction. Part 1. General Requirements” in the form of Appendix D;

- all workers and specialists, before starting work, must undergo training in accordance with the requirements of local regulatory documents on safety, industrial sanitation and fire safety in accordance with clause 4.5 of instructions N P2-01 SP-218 I-001;

- arrange a temporary fencing of the construction site 2 m high, in accordance with GOST 23.407-78;

- install a signal fence around the perimeter of hazardous areas during the operation of construction equipment and mechanisms;

- install an information board, as well as temporary road signs;

- arrange a wash of Neva-2 (or equivalent) wheels in case of equipment leaving for the city;

- disconnect and dismantle utility networks that fall into the building area;

- lay temporary power and water supply networks, arrange electric lighting;

- install administrative buildings;

- install temporary warehouses, sheds;

- deliver to the construction site structures and materials located in storage areas in the required quantity;

- deliver and prepare for operation mechanisms, equipment and installation equipment;

- create a geodetic alignment base;

- equip a specially designated area with primary fire extinguishing equipment;

- provide workers with the necessary tools, equipment, and protective equipment;

- conduct training and briefing of personnel on safety precautions.

2.2 Transportation and storage

The strapping elements should be delivered to the construction site using the MMC FUSO manipulator.

Preparation of metal structures for transportation must comply with GOST 26653. Metal structures with cross-sectional dimensions up to 50 mm inclusive are tied into bundles, skeins or bundles of skeins, and over 50 mm - bundled into bundles at the request of the consumer. Bent profiles are tied into bundles.

The cross-section of packs of metal structures, depending on the size and shape of the cross-section, should approach a circle, rectangle or hexagon. By agreement between the manufacturer and the consumer, a different cross-section of the packs is allowed.

When packing metal structures of measured length, the ends of the bundle must be aligned on one side, the protruding ends on the other side must not exceed the maximum length deviations established in the regulatory documentation (ND) for specific types of rental products. By agreement between the manufacturer and the consumer, packaging without aligning the ends is allowed.

During loading and unloading operations, transportation and storage, metal structures must be protected from mechanical damage, for which they should be laid in a stable position on wooden supports and secured (during transportation) with the help of inventory fasteners, such as clamps, clamps, turnstiles, cassettes, etc. .P. Deformed structures must be rejected and replaced with new ones. Do not drop structures from vehicles or drag them on any surface. During loading, slings made of soft material should be used.

The weight of a pack of metal structures, as well as unpackaged rolled products, should not exceed:

- for manual loading and unloading - 80 kg (up to 25 kg per worker);

- with mechanized loading and unloading - up to 1.6 tons.

The passage of vehicles with metal structures, as well as unloading, must be under the strict control of the person responsible for the safe movement of cargo.

Mineral wool boards and sheet metal are also delivered to the construction site using the MMC FUSO manipulator. The elements and materials received at the construction site are placed in the operating area of ​​the installation crane. All materials must be stored in a position appropriate for transport, sorted by size. It is necessary to store materials under a canopy in conditions that prevent their damage.

2.3 Workplace organization

Workplaces must be illuminated in accordance with the requirements of GOST 12.1.046-85, table 1:

Table 1

Lighting standards for workplaces

Construction sites and work areas

Lowest illumination, lux

The plane in which illumination is normalized

Level of the surface on which illumination is normalized

1. Loading, installation, lifting, unloading of equipment, building structures, parts and materials by cranes

Horizontal

At the sites for receiving and supplying equipment, parts designs and materials

Vertical

On the crane hooks in all positions from the operator's side

2. Non-mechanized unloading and loading of structures, parts, materials and tilting

Horizontal

At cargo reception and delivery sites

3. Installation of structures

Horizontal

Throughout the entire height of the assembly

Vertical

4. Integrated assembly of strapping elements (docking, welding)

Horizontal

At ground or work surface level

Vertical

Throughout the entire height of work

5. Approaches to workplaces

Horizontal

On formworks, platforms and approaches

6. Storage room for small technological equipment and installation materials

Horizontal

At floor level

Concentrations of harmful substances in the air of the working area, as well as noise and vibration levels at workplaces should not exceed established sanitary and hygienic standards.

Microclimate parameters must comply with sanitary rules and standards for hygienic requirements for the microclimate of industrial premises.

Machines and units that create noise during operation should be operated in such a way that sound levels in workplaces, areas and on the construction site do not exceed the permissible values ​​​​specified in sanitary standards.

When operating machines, as well as when organizing workplaces, to eliminate the harmful effects on workers of increased noise levels, the following should be used:

- technical means (reducing machine noise at the source of its formation; the use of technological processes in which sound levels at workplaces do not exceed permissible levels, etc.);

- remote control;

- individual protection means;

- organizational measures (choice of a rational mode of work and rest, reducing the time of exposure to noise factors in the work area, treatment, preventive and other measures).

Areas with sound levels above 80 dBA are indicated with danger signs. Working in these areas without wearing personal hearing protection is not permitted. Workers are not allowed to stay in areas with sound levels above 135 dBA.

Production equipment that generates vibration must meet the requirements of sanitary standards.

2.4 Geodetic works

During the work, geodetic control is carried out. Control consists of checking compliance with basic design requirements. Geodetic control should be carried out directly during the execution of work, after completion of work at the site or site, when accepting work from the performers.

Alignment work begins with reference to the reference geodetic base; during the construction process, the work must ensure that it is carried out in situ from the points of the geodetic alignment base with a given accuracy of axes and marks.

A geodetic alignment basis for construction should be created taking into account:

- design and existing placement of buildings (structures) and utility networks at the construction site;

- ensuring the safety and stability of signs fixing the points of the alignment base;

- geological, temperature, dynamic processes and other influences in the construction area that may have an adverse effect on the quality of construction of the alignment base;

- use of the created geodetic alignment base during the operation of the constructed facility, its expansion and reconstruction.

The accuracy of constructing the construction site alignment network should be taken in accordance with the data given in SNiP 3.01.03-84*.
________________
* SNiP 3.01.03-84 is not valid. Instead, SP 126.13330.2012 “Geodetic work in construction. Updated edition of SNiP 3.01.03-84” was put into effect. - Database manufacturer's note.


During the operational period the following is checked:

- safety and immutability of the position of the plan-height base;

- compliance with the setting out of structural elements and alignment axes;

- accuracy of transfer of the main axes of structures;

- correctness of the plan-height position of all structural elements.

During the acceptance control process upon completion of construction, the following is controlled:

- compliance of all geometric parameters of the earthen structure with the requirements of the project and regulatory documents;

- timely and reliable completion of as-built surveys during the construction of column block linings and upon its completion.

The result of this work is as-built geodetic documentation.

Geodetic foundation signs must be supervised during the construction process. Their safety and stability are constantly checked.

All geodetic work during the construction period must be recorded in a work log, which is maintained in parallel with the general work log by the supervisor directly carrying out the construction of this facility.

All executive geodetic documentation is signed by the performing surveyor, chief engineer or person responsible for the work. Acceptance and delivery documentation includes:

- As-built surveys of the mounted piping elements of the column block.

All diagrams indicate the design and actual dimensions or deviations from the design dimensions in height and in plan. The coordinate and elevation system is local. The relative level of 0.000 is taken to be 276.150.

Signed as-built surveys are transferred to the Customer along with acts for hidden work to confirm the scope of work completed.

General management of geodetic control is assigned to the chief engineer.

The results of control observations are recorded in journals.

Table 3

List of equipment and tools for geodetic work

Name of equipment, tools

Note

Total station

Level

Leveling rod

Geodetic pole

StandardIf the payment procedure on the payment system website has not been completed, cash
funds will NOT be debited from your account and we will not receive payment confirmation.
In this case, you can repeat the purchase of the document using the button on the right.

An error has occurred

Payment was not completed due to a technical error, funds from your account
were not written off. Try waiting a few minutes and repeating the payment again.

AKB Monolit has been developing PPR for more than 10 years.
The PPR for the installation of metal structures is developed by our specialists based on the initial data provided by the PPR customer.
The PPR for the installation of metal structures for construction organizations is the main organizational and technological document developed for the purpose of safe construction of the building. The presence of a PPR indicates the readiness of the construction organization to begin construction and installation work.

Initial data for ordering PPR for installation of metal structures
1) Assignment for the development of PPR;
2) Construction Organization Project (COP);
3) Working documentation (DM);

Composition and content of PPR for installation of metal structures
1) Work schedule;
2) Construction master plan (stroygenplan);
3) Schedule of arrival of metal structures at the site;
4) Schedule of movement of workers around the facility;
5) Schedule of movement of the main construction vehicles around the site;
6) Technological diagrams (maps) for the installation of metal structures;
7) Explanatory note containing:
- solutions and instructions for the installation of metal structures;
- requirements for quality and acceptance of work;
- safety and labor protection requirements;
- fire safety requirements;
- environmental protection measures.

The PPR developed by our specialists provides for measures to ensure the stability of metal structures, taking into account their design and layout solutions (including installation connections), the material of structural elements and local conditions.

The stability and geometric immutability of mounted structures of buildings and structures is ensured by compliance with the technological sequence of installation of structural elements and blocks. This is achieved by our specialists dividing the building (structure) in plan and height into separate stable sections (spans, floors, tiers), the installation sequence of which ensures the stability and immutability of the mounted structures in this section.

Even before the start of the installation of metal structures at the construction site, according to the construction organization project (CDP), the work of the preparatory period, the excavation work and the “zero cycle” work must be completed.

Parts of steel structures are usually manufactured at the plant in accordance with the requirements of standards or technical specifications for products of specific types, types and brands according to working documentation (KM, KMD), approved by the developer and accepted for production by the manufacturer.

Work on enlarging steel structures and preparing them for installation is carried out using a load-lifting crane (truck, crawler or tower). The choice of a load-lifting crane can be carried out during the development of a work execution project (WPP), but with mandatory coordination with the organization that developed the construction organization project (COP).

As a rule, the installation of load-bearing metal structures of one-story buildings is carried out in the following technological sequence:

1) Installation of metal columns of the building. The installation of columns begins with a tie panel. If for some reason the specified requirement cannot be met, then it is necessary to install a temporary bonded panel from the first installed columns of the row, beam or spacer and temporary vertical connections between them, installed below the level of the beam (spacer). Then the next column is installed and secured to the temporary bracing panel with a beam or spacer.

2) Installation of coating structures. Installation of metal roofing structures begins with a bonded panel, and if this is not possible, then with any panel, establishing horizontal and vertical connections between adjacent trusses. The next truss to be installed must be secured to the bracing panel with a spacer.

When installing load-bearing metal structures of multi-story buildings, after installing the columns, crossbars are mounted along the axis, ensuring the stability of the resulting frame in the transverse direction. In the longitudinal direction, stability is ensured using vertical connections along the columns and spacer elements. If the stability of the building in the longitudinal direction is ensured by wall structures (which should be indicated in the working documentation), then they should be installed simultaneously with the frame and floors.

In all cases, during the construction of buildings, a mandatory condition is the complete readiness of the assembled steel structures in the section for subsequent work, regardless of the state of installation of the structures in adjacent sections.

The installation of steel structures is usually carried out by teams of workers, each of which includes: assemblers, electric welders, crane operators, and general workers.

Mounted columns, beams and purlins (trusses) must be prepared in advance and placed in the operating area of ​​the crane.

The area where metal structures are being installed must have a temporary fence to prevent unauthorized persons from entering the work area. A temporary road must be laid along the perimeter of the building or structure being constructed to move the installation crane and transport steel structures to the installation site. There should also be storage areas for load-handling devices, a stand with sling diagrams and a table of load weights, spotlights for illuminating workplaces at night, and a wheel washing station.

At PPR, our specialists develop diagrams of horizontal and vertical connections for a load-lifting crane when installing metal structures of a building or structure.

Installation work must begin after delivery and acceptance of the foundations of a building or structure - column supports, if there is an act for hidden work. During the acceptance process, an instrumental quality check of previously completed work must be performed. When checking, the position of the transverse and longitudinal axes of the foundation-supports in plan and the elevation marks of the supporting surfaces of the foundations must be determined.

Installation of metal structures is carried out “bottom-up”, in sections (clamps), using the “crane” method. The installation sequence is developed in the PPR and it must ensure stability and geometric immutability of structures.

Welding or bolting connections are made only after checking the correct installation of structures.

PPR for installation of sandwich panels

Installation of enclosing structures made of lightweight profiled sheets or wall and roof “sandwich panels” is usually carried out in a separate process after the installation of load-bearing metal structures.

Installation of steel profiled sheets of walls and roofs is carried out according to markings that ensure fixation of the calculated width of the profiled sheet (the distance between the axes of the outer corrugations).

Fastening of profiled sheets of roofing and walls to the load-bearing elements of the metal frame of a building or structure is carried out using self-tapping or self-drilling screws or by shooting with dowels in accordance with the requirements of the working documentation (DD).

Installation of wall and roof sandwich panels is carried out panel by panel. Slinging of panel packages is carried out only using strappings with vertically located slings. Slinging of “sandwich panels” during installation is carried out only using flexible fabric slings or other methods, including using special traverses, which prevent jamming of the metal edges of the panels and damage to the paint layer.

Sealing gaskets in the vertical and horizontal joints of the sandwich panels are laid before the panels are installed.

The enlarged assembly of walls from light panels into cards is carried out on stands in the operating area of ​​a load-lifting crane. Maximum deviations of maps are carried out according to the working design.

All linings of horizontal and vertical joints, as well as corner elements of panels, are placed on sealant to prevent moisture from entering the joint.

If there are no special requirements in the working documentation for deviations of the mounted wall and roof panels, they should not exceed standard values.

Types of installation connections when developing PPR

When installing metal structures, various types of installation connections are used:

1) Installation connections without controlled bolt tension. This type of installation connections includes shear bolted connections, in which external forces are perceived due to the shear resistance of the bolts and the shear resistance of the connected elements. When assembling such mounting connections, the holes in the structural parts must be aligned and secured against displacement of the parts with assembly plugs, and the assembled packages must be tightly bolted.

2) Mounting connections with high-strength, tension-controlled bolts. Installation connections with high-strength, tension-controlled bolts include:

Friction and shear-resistant connections, in which external forces are perceived due to the resistance of frictional forces arising along the contact planes of the connected elements from the pre-tensioning of the bolts;

Friction-shear assembly connections, in which external forces are perceived mainly by overcoming the compression resistance of the flanges from the pre-tensioning of high-strength bolts.

3) Special installation connections:

Shooting with high-strength dowels;

Installation of self-tapping and self-drilling screws;

Contact spot welding;

Electric rivets;

Folding of longitudinal edges.

A characteristic feature of special installation connections is that to perform them, a one-sided approach to the structural elements being connected is sufficient. The main area of ​​special installation connections used is the fastening of the enclosing structures of buildings or structures.

4) Welded joints. The type of welding equipment is selected depending on the welding method, conditions and features of welding work and the specified parameters of the welding process. Basic welding methods used in the installation of metal structures.

Manual arc welding with coated electrodes. It is a universal and basic welding method for making seams in all spatial positions when enlarging and installing metal structures.

Mechanized welding with self-shielding flux-cored wire. It is used primarily for making connections in the lower position when enlarging structures at the bottom and for welding extended seams at the design level.

Mechanized welding in shielding gases with solid wire. It is used for enlarged welding of structures in the lower position with protection of the welding zone from the wind.

Automated submerged arc welding. It is used for welding straight, extended seams in the lower position when enlarging sheet blanks and structures.